Boss Energy. Boss Energy.

Our track record

07290eae 4845 4d5f be30 b327326ef172 4

Positioned for future growth

07290eae 4845 4d5f be30 b327326ef172 10
  • June 2022

    Final Investment Decision –with production set for December quarter, 2023

  • March 2022

    Front-end engineering study finds costs, technical performance and financial returns will be in line with 2021 feasibility study forecasts.

  • March 2022

    $125M capital raising completed to fully fund development of the Honeymoon Project.

  • June 2021

    Enhanced Feasibility Study delivered, incorporating NIMCIX Ion Exchange columns. The EFS confirmed a mine life of +10 years at a forecast production rate of 2.45Mlb/annum, with the proposed changes to Honeymoon’s processing method cutting all-in sustaining costs (AISC) by 16% to US$25.62/lb and delivering a 35% increase in pre-tax project NPV to US$309 million.

  • March 2021

    Acquisition of 1.25Mlb strategic U3O8 inventory to strengthen off-take and project funding negotiations

  • January 2020

    Feasibility Study confirms Honeymoon as Australia’s next uranium producer with global first mover advantage.

  • April 2019

    Australian Government renews Honeymoon’s Export Permit for 3.3Mlb/annum U3O8, meaning the planned re-start operation is fully permitted.

  • February 2019

    Mineral Resource upgrade - global Resources of 71.6Mlb U3O8, increasing Honeymoon’s re-start area to 36Mlb contained U3O8.

  • March 2018

    Boss increases ownership of Honeymoon Project to 100% with agreement to acquire remaining 20% project interest from Wattle Mining.

  • November 2017

    Field Leach Trial improved leach chemistry results in historic high tenors (>80mg/L U3O8) exceeded plant design.
    Ion Exchange process successfully proved with excellent performance of selected resins on Honeymoon conditions

  • May 2017

    Pre-feasibility Study completed, confirming Honeymoon to be a highly economic project with all-in sustaining costs in the lowest quartile of global producers.

  • March 2017

    Combined Honeymoon Project Resource increased to 63.3Mlb of contained U3O8, including a substantial resource update for the Jasons Deposit.

  • April 2016

    Global Mineral Resource base at the Honeymoon Project increased to 53Mlb of contained U3O8, with the delivery of a maiden Mineral Resource Estimate for the Gould’s Dam deposit, part of the Honeymoon Project’s highly prospective western tenement package.

  • January 2016

    Boss delivers a substantial increase in the Resource base at the Honeymoon Project to 27.6Mlb of contained U3O8, with the Resource grade of 820ppm making Honeymoon one of the highest-grade uranium deposits held by an ASX-listed uranium developer.

  • March 2015

    Boss enters into an agreement with Uranium One Inc. to acquire an initial 80% interest in the Honeymoon Uranium Project in South Australia. The project includes a total Mineral Resource inventory of 16.57Mlb of contained U3O8, as well as established infrastructure including a solvent extraction processing plant. The total upfront acquisition cost totals approximately $9.6M, with the acquisition successfully completed in December 2015.

Keep up to date with the latest from Boss Energy

We’ll send you important information regarding upcoming community events and project updates. You can unsubscribe at any time.

Thank you!
Thanks for subscribing! Look out for our important information regarding upcoming community events and project updates in your inbox.